Kingpost Retaining Wall

Project Name: East Grinstead
Project Description: Installation of 100m Kingpost Retaining Wall
Contract Value: Circa £80,000
Duration of works: 2 x 24 Hour Weekend Possessions

Engaged initially for plant supply only, TRS negotiated the supply of labour to install the 100m of kingpost walling. The works consisted of augering 450mm holes in the cess and the installation of 'H' beams at 2m centres. GRP planks were then installed and concreted into position. Works were undertaken during isolations over two weekend possessions using multiple machines for each discipline. Excavated material was then removed from the toe of the cutting and taken back to the RRAP for disposal off site. All works were completed on time and on budget.

"A big thank you to you and your team for a great job. All of your operatives worked well as a team to get the job done and i was very impressed with the quality of the workmanship" 

Coment from Craig Ross, Dyer & Butler Site Agent